Bridge ready but lies idle sans approach roads
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Saturday
February 04, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
SATURDAY, FEBRUARY 04, 2023
Bridge ready but lies idle sans approach roads

Transport

Kazi Moniruzzaman
08 May, 2021, 02:00 pm
Last modified: 08 May, 2021, 02:00 pm

Related News

  • Shariatpur transport sector booms in 7 months since Padma Bridge opening
  • 6 killed on spot as ambulance crashes into truck in Shariatpur
  • Two risky bridges cause Shariatpur people to suffer
  • 3 die after launch hits bridge in Shariatpur 
  • People continue to suffer while five collapsed bridges yet to be rebuilt

Bridge ready but lies idle sans approach roads

Although the approach roads are scheduled to be completed by June 2021, only 50% of the work has so far been completed

Kazi Moniruzzaman
08 May, 2021, 02:00 pm
Last modified: 08 May, 2021, 02:00 pm
The bridge over the River Kirtinasha in Shariatpur’s Naria Upazila was built spending Tk9.8 crore over one and a half years ago. But it lays idle as only 50% construction work of the roads connecting to the bridge has been completed so far. Photo: TBS
The bridge over the River Kirtinasha in Shariatpur’s Naria Upazila was built spending Tk9.8 crore over one and a half years ago. But it lays idle as only 50% construction work of the roads connecting to the bridge has been completed so far. Photo: TBS

One and half years have gone past since a bridge over the River Kirtinasha close to Vojeshwar river port in Shariatpur's Naria upazila was constructed, but villagers are still suffering because approach roads connecting to the bridge have not been built yet.

The bridge that was built at a cost of Tk9.8 crore to ease suffering of people in Naria and Zajira upazilas is now lying idle. 

The Local Government Engineering Department (LGED) in the district paid the bill to two contractors of the bridge project although they did not build the connecting roads on both sides of the bridge – in Gourail village in Vojeshwar union beside the river port, and Char Vojeshwar village in Japsha union - owing to complications in land acquisition. 

The LGED later revised the project that started in 2016 and discarded the approach road construction plan, according to the department. 

Following the revised plan, the contractors named Kamarjani Brozen and Anowara built a 10-metre box culvert and a 80-metre embankment on both sides of the river instead of constructing the roads.

Later, on 18 July 2019, the LGED started building the link roads at a cost of Tk13.21 crore under a new project.

Although the link roads are supposed to be completed by June 2021, only 50% of the work has so far been completed. 

A 162-metre link road from Gourail to Mosura village's Dr Jalil Bari area, and another 303-metre link road through Char Vojeshwar village to Japsha Kheya Ghat were supposed to be built. 

But there appeared a problem in acquiring land in Char Vojeshwar. The land was private property and owners were unwilling to give the land to the government, according to Md Sahabuddin Khan, Naria upazila engineer. 

Md Sahabuddin said, "The construction of the connecting roads could not be done as the scheduled time of completing the project was over, and there were complications over land acquisition for building the roads." 

"Due to the complications in land acquisition, the LGED started making the link roads using RE Wall technology. This is a new technology which makes it possible to build roads using less space. It is taking time to finish the work as it is a new technology. We are not wasting time. Hopefully, the work will be completed soon," he said.        

If the 99-metre long bridge opens, residents of at least 150 villages in Naria and Zajira upazilas will be able to go to Shariatpur town, Dhaka, and other places easily.  It will also cost less to transport agricultural goods.  

The bridge over the River Kirtinasha in Shariatpur’s Naria Upazila was built spending Tk9.8 crore over one and a half years ago. But it lays idle as only 50% construction work of the roads connecting to the bridge has been completed so far. Photo: TBS
The bridge over the River Kirtinasha in Shariatpur’s Naria Upazila was built spending Tk9.8 crore over one and a half years ago. But it lays idle as only 50% construction work of the roads connecting to the bridge has been completed so far. Photo: TBS

Bonnya Begum from Gourail village in Vojeshwar union said they have not benefitted from the bridge because it has no approach roads. They still have to cross the river by boat, and after 9 pm at night, there are no boats, she said. 

Patients suffer the most, she added.

Arif Bepari, an auto-rickshaw driver from the Japsha union, said, "We now have to travel a long distance to go to Shariatpur town. If the bridge opens, the distance will come down to eight kilometres. Right now, without the bridge, our vehicles often get damaged as the roads we use are dilapidated."

Shamim Hossain was waiting for a boat at the Vojeshwar river port Ghat (terminal) with his motorbike to go to Char Vojeshwar. He said accidents were very common there while crossing the river, especially, during the monsoon.

People still have to risk their lives as there is no alternative now, he said. But if the bridge opened, it would take only five minutes to go to Japsha union, he added.

Bangladesh / Top News

Shariatpur / bridge / Government Engineering Department (LGED)

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Some tough tasks on the plate for Bangladesh Bank!
    Some tough tasks on the plate for Bangladesh Bank!
  • Having sufficient reserves, strong social security needed to be safe in bad time
    Having sufficient reserves, strong social security needed to be safe in bad time
  • Resilience should be built to cope with long-term implications
    Resilience should be built to cope with long-term implications

MOST VIEWED

  • Metro rail may reduce the need for people to live near workplaces. Photo: TBS
    Tk2.46cr earned from metro rail since opening
  • Representational Image
    Underground metro to cut airport-Kamalapur travel time to 25 minutes
  • File photo. Prime Minister Sheikh Hasina is expected to inaugurate work on the Bangabandhu Railway Bridge on 29 November. Photo: UNB
    Bangabandhu Rail Bridge will open earlier than expected: Railways minister
  • Representational image. Photo: Collected
    PM to open underground metro construction on 2 Feb
  • No new roads before national election: Obaidul Quader
    No new roads before national election: Obaidul Quader
  • Photo: TBS
    Transport strike in Sylhet from Monday to demand release of Chhatra Dal leader

Related News

  • Shariatpur transport sector booms in 7 months since Padma Bridge opening
  • 6 killed on spot as ambulance crashes into truck in Shariatpur
  • Two risky bridges cause Shariatpur people to suffer
  • 3 die after launch hits bridge in Shariatpur 
  • People continue to suffer while five collapsed bridges yet to be rebuilt

Features

Sketch: TBS

Say 'Salud' before your salad main course

12h | Food
Coots running. Photo: Enam Ul Haque

Cute Coot of Baikka Beel: 'And yet he was as bald as a coot'

6h | Panorama
With only one government run specialised cancer hospital in the capital — the National Institute Of Cancer Research and Hospital (NICRH) in Mohakhali — patients have no option but to resort to private hospitals. Photo: Noor A Alam.

Cancer care: Medical treatment and beyond

13h | Panorama
Andy Mukherjee. Sketch: TBS

What makes India's billionaires' support special for Adani

1d | Panorama

More Videos from TBS

Prioritise medical equipment, raw material imports over luxury items

Prioritise medical equipment, raw material imports over luxury items

4h | TBS Round Table
Adani row rocks India’s parliament

Adani row rocks India’s parliament

3h | TBS World
Concord launches new plant to produce environment friendly bricks

Concord launches new plant to produce environment friendly bricks

9h | TBS Stories
How Asif Khan would invest his fresh funds right now

How Asif Khan would invest his fresh funds right now

9h | TBS Markets

Most Read

1
Leepu realised his love for cars from a young age and for the last 40 years, he has transformed, designed and customised hundreds of cars. Photo: Collected
Panorama

'I am not crazy about cars anymore': Nizamuddin Awlia Leepu

2
Photo: Collected
Energy

8 Ctg power plants out of production

3
The International Monetary Fund (IMF) logo is seen outside the headquarters building in Washington, U.S., September 4, 2018. REUTERS/Yuri Gripas/File Photo
Economy

IMF approves $4.7 billion loan for Bangladesh, calls for ambitious reforms

4
Fund cut as Dhaka's fast-track transit projects on slow spending lane
Infrastructure

Fund cut as Dhaka's fast-track transit projects on slow spending lane

5
Photo: Collected
Court

Japanese mother gets guardianship of daughters, free to leave country

6
Belal Ahmed new acting chairman of SIBL
Banking

Belal Ahmed new acting chairman of SIBL

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net