Slowdown in fast-track projects still a concern
Skip to main content
  • Home
  • Economy
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
  • Epaper
  • More
    • Subscribe
    • COVID-19
    • Bangladesh
    • Splash
    • Videos
    • Games
    • Long Read
    • Infograph
    • Interviews
    • Offbeat
    • Thoughts
    • Podcast
    • Quiz
    • Tech
    • Archive
    • Trial By Trivia
    • Magazine
    • Supplement
  • বাংলা
The Business Standard

Monday
August 08, 2022

Sign In
Subscribe
  • Home
  • Economy
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
  • Epaper
  • More
    • Subscribe
    • COVID-19
    • Bangladesh
    • Splash
    • Videos
    • Games
    • Long Read
    • Infograph
    • Interviews
    • Offbeat
    • Thoughts
    • Podcast
    • Quiz
    • Tech
    • Archive
    • Trial By Trivia
    • Magazine
    • Supplement
  • বাংলা
MONDAY, AUGUST 08, 2022
Slowdown in fast-track projects still a concern

Bangladesh

Saifuddin Saif
15 October, 2020, 10:35 pm
Last modified: 16 October, 2020, 01:32 am

Related News

  • What is for the poor in govt staff salary, project costs?
  • Global business is enduring a synchronised slowdown
  • BGMEA urges govt to expedite mega projects’ implementation 
  • China’s slowdown poses threat for global recovery
  • Chinese economy risks deeper slowdown than markets realise

Slowdown in fast-track projects still a concern

Work on the projects is not getting back expected pace in the absence of foreign workers

Saifuddin Saif
15 October, 2020, 10:35 pm
Last modified: 16 October, 2020, 01:32 am

Less than 8% of the allocation for the Padma Multipurpose Bridge Project was spent in the first quarter of the current fiscal year, though much of the physical work of the bridge is visible by now.

The progress of work of the metro-rail project in Dhaka city has been slow although enough money has been kept aside for the priority project to make sure the flagship transport infrastructure opens for public on the 50th Victory Day.

This is the situation of the fast-track projects whose work resumed after three-months closure caused by Covid-19 outbreak but have not yet gained the desired pace.

Authorities said prolonged absence of foreign consultants and employees due to pandemic was the main reason behind the slow pace of top priority infrastructure projects, making their timely implementation uncertain.

Despite resumption of work after a few months of suspension due to the pandemic, the government's high priority fast-track projects are still to pick up enough speed as most foreign experts and consultants – stay stranded in their respective countries.

According to a report, prepared by the Economic Relations Department (ERD), project works remained suspended for a long time mainly due to the pandemic. The report on the progress of eight fast-track projects in the first quarter (July-September) of the ongoing fiscal year was forwarded to the Prime Minister's Office on 7 October.

Work on the Padma Bridge is not getting back momentum as one-third of the project’s foreign workers still remain stranded in China. Photo: Mumit M/TBS
Work on the Padma Bridge is not getting back momentum as one-third of the project’s foreign workers still remain stranded in China. Photo: Mumit M/TBS

To accelerate economic activities and increase growth, the government identifies some priority projects as fast-track ones and closely monitors their implementation for faster completion.

The allocation for the eight fast-track projects in the fiscal 2020-21 is Tk42,433 crore. As of September, around 9% or Tk3,835 crore has been spent on the projects from the allocation.

Pradip Ranjan Chakraborty, secretary to the Implementation Monitoring and Evaluation Division (IMED), said the fast-track projects have not yet picked up expected pace due to Covid-19 effects. The IMED has already met with the implementing agencies to decide what to do in this regard.

Weather also holds back Padma Bridge work

Bad weather conditions have dealt another blow to the construction of the Padma Bridge which is already reeling under the pandemic shocks.

The ERD report says, in the first quarter, the Bridges Division spent only 7.48% of the Padma Multipurpose Bridge Project's allocation amounting to Tk5,000 crore earmarked for the fiscal year, with the physical progress being 81.5%. Construction of the main bridge has made a progress of 90% while 74.50% of river training work has been completed.

Padma Bridge Project Director Shafiqul Islam said work on the Padma Bridge has not got the expected pace due to high water and current in the river during the monsoon season. Covid-19 still remains a stumbling block, he said.

PHOTO: Mumit M/TBS
PHOTO: Mumit M/TBS

Besides, the project work is not getting back momentum as one-third of the foreign workers are still stranded in China. However, work is underway to install two to three more spans this month, even with the limited number of manpower.

The 32nd span of the total 41 spans of the bridge was installed on 11 October, thus making 4,800 metres of the much-awaited bridge visible.

However, officials at the Bridges Division think that it will not be possible to complete the construction of the Padma Bridge within the expected time.

Although the work is scheduled to be completed by June 2021, its deadline may be extended to 2022, they added.

Padma rail link expected to get back pace

There was not much progress in the implementation of the Padma Bridge rail link project in the last fiscal year owing to complexities over loan agreement and Covid-19.

Bangladesh Railway hopes that the project implementation will be expedited in the current financial year.

The project is being implemented on a government-to-government (G2G) basis with funding from the Chinese government. The ERD report said the project was revised as its progress on spending was not as expected because of complications over land acquisition and its design remaining unfinished.

In the first three months of the current fiscal year, the project has witnessed a 15.71% expense from its allocation of Tk2500 crore fixed for the current fiscal year.

The project's physical progress is around 26%. However, railway officials said they cannot restart work in full swing in the absence of many Chinese workers who have not yet returned to work. 

Only 6% of Tk5,583 crore allocated for the current fiscal year was spent on the metro rail project (Uttara-Motijheel) in the first quarter. Photo: Mumit M/TBS
Only 6% of Tk5,583 crore allocated for the current fiscal year was spent on the metro rail project (Uttara-Motijheel) in the first quarter. Photo: Mumit M/TBS

Uncertainty over opening metro rail on time

The first phase of the metro rail project (Uttara-Motijheel) has been targeted to be inaugurated on December 16, 2021 – the golden jubilee of Bangladesh's independence.

But its work has not made the expected progress in the first three months of the current fiscal year, putting in doubt the much-hyped project's inauguration within the deadline.

Only 6% of Tk5,583 crore allocated for the current fiscal year was spent on the project in the first quarter.

Seeking anonymity, an official at the Dhaka Mass Transit Company Ltd (DMTCL), which is implementing the project, said the metro rail work resumed after a temporary shutdown, but it will take more time for normal pace to come back as many Japanese experts and consultants have not returned to Bangladesh yet.

The Japanese officials have been assured of all possible health safety measures. Hopefully, they will come to Bangladesh soon and join their work, he added.

File Photo: The work of metro rail project (Uttara-Motijheel) underway. Photo: Mumit M/TBS
File Photo: The work of metro rail project (Uttara-Motijheel) underway. Photo: Mumit M/TBS

MAN Siddique, managing director at the DMTCL, told The Business Standard, "We are working for the timely implementation of the Mass Rapid Transit (MRT) Line -6, complying with health guidelines and maintaining social distancing."

"We are still hopeful of finishing its work on time," he added.

There is a possibility of the second wave of Covid-19 breaking out this winter. If something like that happens, the work may not be completed within the announced time, MAN Siddique also said.

According to the ERD report, the overall progress of the metro rail is 53.37%.

Lowest progress in Rooppur nuclear project

The Rooppur Nuclear Power Plant, the country's largest project in terms of cost, has made the least progress if spending from its allocated fund in the first three months of the fiscal year is considered.  The project authorities could spend only 4.58% from Tk15,991 crore during the period.

The Tk1,13,093 crore project is expected to be implemented by 2025.

The overall progress of the project has been 28.7% till now. The units of the nuclear power plant will generate 1,200 megawatts each once they go into operation.

The Tk1,13,093 crore project of Rooppur Nuclear Power Plant is expected to be implemented by 2025. However, The overall progress of the project has been 28.7% till now. Photo: Mumit M/TBS
The Tk1,13,093 crore project of Rooppur Nuclear Power Plant is expected to be implemented by 2025. However, The overall progress of the project has been 28.7% till now. Photo: Mumit M/TBS

Project Director Dr Shaukat Akbar claimed the project work has not slowed down. The low progress is shown as the amount of foreign loans has not been calculated yet. This calculation will be done from October.

Rampal power plant sees slow progress in absence of foreign workers

According to the progress report for the fast-track projects, the Rampal power plant project saw only 5.8% spending in the first quarter from Tk4,487 crore in allocation for the fiscal year.

The project, which began in 2009, has not even made half of the physical progress yet. 

Project officials said Indian and Bangladeshi workers cannot join work because of Covid-19. Workers from both countries are expected to join work in November. Then, the work will pick up pace and the slack will be made up.

The Payra deep seaport, another fast-track project, saw spending of only 0.03% from its allocation set for the current fiscal year. Photo: Mumit M/TBS
The Payra deep seaport, another fast-track project, saw spending of only 0.03% from its allocation set for the current fiscal year. Photo: Mumit M/TBS

Slow pace of Dohazari-Cox's Bazar-Gundum rail line construction

Only 10.37% of the Dohazari-Cox's Bazar-Gundum rail line construction project has been spent in the first three months of the fiscal year. The project's overall physical progress has been 43%, according to the ERD report.

From the beginning, the project had suffered some complexities in land acquisition. Now the pandemic has slowed its implementation too, said project officials.

Matarbari power project sees good progress

The Matarbari coal-fired power plant is the only fast track project that has made good progress with 30% of this fiscal year's allocation having been spent till September. 

But, the progress in the project implementation is much lower than planned.

Official boats are docked at the jetty of Payra Port Authority on the Andharmanik River at Kalapara in Patuakhali. Photo: Mumit M/TBS
Official boats are docked at the jetty of Payra Port Authority on the Andharmanik River at Kalapara in Patuakhali. Photo: Mumit M/TBS

Meanwhile, the Payra deep seaport, another fast-track project, saw spending of only 0.03% from its allocation set for the current fiscal year. However, 41% of the total allocation for the construction of the first terminal of the port has been spent in the first three months.

Top News

slowdown / fast-track / projects

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Noor-A-Alam
    Dollar price reaches highest ever Tk115 in kerb market
  • Interbank dollar exchange rate rises to Tk95
    Interbank dollar exchange rate rises to Tk95
  • PM sketches Bangmata's key-shadow role in independence struggle
    PM sketches Bangmata's key-shadow role in independence struggle

MOST VIEWED

  • The number of intra-city buses in the capital decreased significantly since Saturday morning following the government's move to hike fuel prices. The photo shows an empty Farmgate, one of the busiest Dhaka intersections, on Saturday, 6 August, 2022. taken Photo: Rajib Dhar/TBS
    Public transport shortage grips commuters across Bangladesh after fuel price hike
  • Infographic: TBS
    Rail engines bought without feasibility study fail to ease locomotive crisis
  • Photo: TBS
    First Russian ship arrives at Mongla since start of Ukraine invasion
  • Represenatational image. Picture: Collected
    DNCC to launch smart parking for 500 vehicles in September
  • Photo: TBS
    Mongla port to auction off 115 cars
  • Prime Minister Sheikh Hasina. Sketch: TBS
    PM offers Nepal use Mongla, Chattogram seaports

Related News

  • What is for the poor in govt staff salary, project costs?
  • Global business is enduring a synchronised slowdown
  • BGMEA urges govt to expedite mega projects’ implementation 
  • China’s slowdown poses threat for global recovery
  • Chinese economy risks deeper slowdown than markets realise

Features

Photo: BSS

Begum Fazilatunnessa Mujib . . . woman of moral power

2h | Thoughts
Will Glass Cosmetics be your next skincare holy grail?

Will Glass Cosmetics be your next skincare holy grail?

6h | Brands
Akij Tableware: More than just dishes on a table

Akij Tableware: More than just dishes on a table

7h | Brands
Deeply depressed and afraid of living in total darkness, the Noakhali-based housewife Rasheda desires nothing but to get her vision back. Photo: Noor-A-Alam

Blind people need 25,000 corneas. Sandhani gets around 25

8h | Panorama

More Videos from TBS

Challenges the world will face after 10 years

Challenges the world will face after 10 years

2h | Videos
Ukraine-Russia war at new stage, fear of nuclear radiation increasing

Ukraine-Russia war at new stage, fear of nuclear radiation increasing

3h | Videos
First Aid for Stroke: What you should know

First Aid for Stroke: What you should know

6h | Videos
Is smartphone use reducing our memory?

Is smartphone use reducing our memory?

7h | Videos

Most Read

1
Diesel price hiked by Tk34 per litre, Octane by Tk46
Energy

Diesel price hiked by Tk34 per litre, Octane by Tk46

2
Housing projects sprouting up by Dhaka-Mawa expressway
Real Estate

Housing projects sprouting up by Dhaka-Mawa expressway

3
July remittance hits two-year high
Economy

July remittance hits two-year high

4
Infographic: TBS
Banking

Dollar rate will be left to market after two months: Governor

5
Bangladesh to resume talks for Ukrainian wheat import
Economy

Bangladesh to resume talks for Ukrainian wheat import

6
A liquefied natural gas (LNG) tanker is tugged towards a thermal power station in Futtsu, east of Tokyo, Japan November 13, 2017. REUTERS/Issei Kato/File Photo
Energy

Summit proposes long-term LNG supply to Petrobangla

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2022
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net