Fund cut as Dhaka's fast-track transit projects on slow spending lane
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Wednesday
March 22, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
WEDNESDAY, MARCH 22, 2023
Fund cut as Dhaka's fast-track transit projects on slow spending lane

Infrastructure

Jahidul Islam & Saifuddin Saif
29 January, 2023, 01:00 pm
Last modified: 29 January, 2023, 03:35 pm

Related News

  • Authorities dismantle faulty BRT ramp after wasting time, money
  • Metro magic is here, now
  • Metro Rail Line-6 alone to save Tk3,500cr in travel time, vehicle operation cost yearly
  • Earning sources beyond fares
  • From concrete mess to a green relief: Metro Rail set for inauguration

Fund cut as Dhaka's fast-track transit projects on slow spending lane

Road transport high-ups note the spending appetite for the projects dwindles on the back of poor implementation

Jahidul Islam & Saifuddin Saif
29 January, 2023, 01:00 pm
Last modified: 29 January, 2023, 03:35 pm

Five projects, including the airport-Kamalapur underground metro train, aiming at an integrated and swift rail rapid transit for Dhaka have proposed around 50% allocation cut this year, show documents, as the works clocked less than 20% progress in the first half of FY23. 

The five projects had around Tk8,269 crore allocation for FY23, including government and foreign funding. The fund trimming proposals amounted to Tk4,105 crore – around Tk1,583 crore from the government and Tk2,521 crore from the foreign parts.

The implementing agency Dhaka Mass Transit Company Limited (DMTCL) attributed the slow progress and subsequent budget trimming to land acquisition hiccups, tangled up utility lines and tender issues. 

However, the Budget Management Committee of the Road Transport and Highways Division labelled the fund cut proposal for the government's fast-track projects "disappointing" and pinned the blame on DMTCL's "inefficiency", according to meeting minutes.         

Against the backdrop, the physical work of Mass Rapid Transit (MRT) Line-1 – connecting Dhaka airport to Kamalapur with an elevated link from Natun Bazar to Purbachal by an underground metro rail – is going to be inaugurated on 2 February. 

Prime Minister Sheikh Hasina will inaugurate the country's first underground rail construction with MRT-1's depot work at Purbachal. The Executive Committee of the National Economic Council (Ecnec) commissioned the MRT-1 in October 2019 at an estimated Tk52,561 crore.   

But prior to commencing the MRT-1 physical work even after three years, the DMTCL has proposed to cut around Tk1,792 crore, which is about 79% of the total allocation of Tk2276 crore for FY23.

In the current fiscal year, the state-owned company wants to bring down the MRT-1 budget to Tk483 crore thanks to the slow pace of work.

The Budget Management Committee meeting expressed concern over the slower implementation of the priority projects and refunding of a substantial amount from the original allocation in the annual development programme.

Referring to the government's project line-up rearranging due to fund crunch, participants at the meeting said adequate allocations have been kept aside for metro rail projects with the highest priority even amid the crisis. 

The proposals for fund cuts were mostly attributed to "inefficient" implementation, which was regarded as "disappointing".

The meeting urged the DMTCL authorities to speed up the spending in the next fiscal year to catch up with the allocations.  

Md Abul Kashem Bhuiyan, project director of MRT-1, said, "We had a plan of awarding three contract packages to construct the main line from airport to Rampura in the current fiscal year. We surrendered the allocation as we failed to do so."

He shifted the blame to the pandemic that delayed the preparatory works such as basic design, detailed design and land acquisition. He also accused the Japan International Cooperation Agency (Jica), the foreign financier, of delays in making some key decisions.

"The Jica was supposed to provide some observations on land acquisition within one month. But the lender took five months to do so," he told The Business Standard.

In October 2019, the Ecnec also approved MRT Line-5 (Northern Route) at Tk41,238 crore to develop rapid metro transit connecting Hemayetpur and Bhatara via Gabtoli, Mirpur-1, 10 and 14, Banani, Gulshan-2 and Natun Bazar. 

The project has Tk800 crore allocated in FY23, but the project authorities seek to reduce it by 49.24% to Tk406 crore in the revised development budget. 

Aftab Hossain Khan, director for MRT-5 project, told The Business Standard they proposed surrendering the money as there is no big payment in the upcoming months.

He said the project, which now is at the design stage, has already acquired lands and would require more money flow next fiscal year for land development.  

"We hope the depot construction will begin in July or August in FY24. We then will be able to catch up with the allocation," he said.

The MRT Line-6 project between Uttara to Motijheel was inaugurated partially in December last year. Though project officials claim the work is progressing fast to extend the services up to Motijheel within 2023, MRT-6 is going to surrender about Tk1,914 crore from its Tk4,963 crore allocation in FY23.

Despite repeated attempts, The Business Standard could not reach MRT-6 Project Director Md Aftabuddin Talukder for comments.

Economy / Infograph / Top News

Transit projects / Mass Rapid Transit (MRT) / Bus Rapid Transit (BRT)

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Bangladesh Railway Fans' Forum
    Bus-train collision snaps rail link between Dhaka and rest of country
  • ADP implementation progress record low in first eight months of FY23
    ADP implementation progress record low in first eight months of FY23
  • File photo
    Ramadan goods prices soar over 5% in a week

MOST VIEWED

  • Dhaka Metro Rail. Photo: Rajib Dhar
    City planners against metro rail in Chattogram
  • The construction of Patenga Container Terminal is almost complete and the authorities hope vessels can anchor here by June. The terminal is expected to handle four lakh of containers and oil tankers. The photo was recently taken from Patenga. Photo: Mohammad Minhaz Uddin
    Framework signed with Saudi Arabia's RSGT for Patenga Container Terminal concession
  • Matarbari Power Plant. File Photo: BSS
    Matarbari access road work begins in July
  • Dhaka-Ctg 8-lane highway project to begin by end-2024
    Dhaka-Ctg 8-lane highway project to begin by end-2024
  • Photo: Foisal Ahmed
    Construction of Matarbari port progressing at full pace
  • Photo: Collected
    Railways aims to repair Kalurghat Bridge by June, tender next month

Related News

  • Authorities dismantle faulty BRT ramp after wasting time, money
  • Metro magic is here, now
  • Metro Rail Line-6 alone to save Tk3,500cr in travel time, vehicle operation cost yearly
  • Earning sources beyond fares
  • From concrete mess to a green relief: Metro Rail set for inauguration

Features

Collective efforts imperative to water security

Collective efforts imperative to water security

5h | Wellbeing
Photo: TBS

Confronting the global water crisis

10h | Panorama
Of 53,685 hectares of arable land in the Bhabodah area, 28,882 hectares were affected by waterlogging. Photo: Mumit M

3 decades on, a man-made waterlogging crisis lingers in Bhabadaha

10h | Panorama
Photo: TBS

Desalinating the lives of our coastal population

11h | Panorama

More Videos from TBS

What is Interpol red alert?

What is Interpol red alert?

1h | TBS Stories
‘‘Accelerating Change Decentralising the Conversation on Water Stewardship’’

‘‘Accelerating Change Decentralising the Conversation on Water Stewardship’’

5h | TBS Round Table
End of Ukraine war no closer after Putin, Xi talks

End of Ukraine war no closer after Putin, Xi talks

2h | TBS World
Wagner forces capture 70 per cent of Bakhmut

Wagner forces capture 70 per cent of Bakhmut

7h | TBS World

Most Read

1
Md Shahabuddin Alam, managing director (MD) of SA Group. Photo: UNB
Court

SA Group MD, his wife banned from leaving country

2
Photo: Collected
Bangladesh

Mahindra shuts its Bangladesh subsidiary

3
Take a loan, buy the bank - the Southeast way
Banking

Take a loan, buy the bank - the Southeast way

4
Photo: Collected
Crime

Mahiya Mahi arrested in DSA case; sent to jail for 'defaming police'

5
Photo illustration: Steph Davidson; Getty Images
Bloomberg Special

Elon Musk's global empire has made him a burning problem for Washington

6
Photo: Collected
Bangladesh

At least 15 injured as Daffodil University students clash with locals in Savar

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net