Spending Tk2,000cr on Ghorashal power plant does not pay off
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Saturday
February 04, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
SATURDAY, FEBRUARY 04, 2023
Spending Tk2,000cr on Ghorashal power plant does not pay off

Energy

Saifuddin Saif
09 October, 2022, 12:15 pm
Last modified: 09 October, 2022, 03:46 pm

Related News

  • Opec to give $38m for Bangladesh power plant development
  • Bengal Electricity inaugurates commercial Power Plant in Cumilla
  • Power supply in Dhaka: Until Ghorashal working in full capacity, situation not to improve
  • Ghorashal power plant’s unit 5 resumes production after 7 days
  • Power generation at unit 5 of Ghorashal power plant halted since national grid failure

Spending Tk2,000cr on Ghorashal power plant does not pay off

Saifuddin Saif
09 October, 2022, 12:15 pm
Last modified: 09 October, 2022, 03:46 pm
Spending Tk2,000cr on Ghorashal power plant does not pay off

Highlights:

  • Goals are not being achieved due to project design flaws
  • Production increased only 30MW against the target of 199MW
  • Purchase of new parts to achieve target has been proposed
  • Additional cost will be Tk100 crore to Tk150 crore
  • The duration of the project has increased by two times

Massive spending on the repowering of the fourth unit of the Ghorashal power station is not paying off due to flawed design.

The government took the repowering project at a cost of Tk2,072 crore to increase the capacity of the 4th unit of the plant from 210MW to 409MW.

From a pre-commissioning test on 95% completion of the physical work, the authorities have now come to know that the production capacity has increased by just 30MW, against the target of 199MW.

The project implementing authorities say the desired capacity cannot be achieved as the design of the project does not include steam turbines. As the consultancy did not recommend replacing the steam turbine, it was dropped from the design, they added.

Now, if a new steam turbine is installed, the authorities believe that it is possible to generate electricity from this unit as per target. However, an additional Tk100 crore to Tk150 crore will have to be spent on it.

Energy experts have blamed mismanagement and poor planning for the failure to achieve the target. With the money spent on repowering, it was possible to set up a new power plant of 200-250MW – including land acquisition.

The 210MW 4th unit went into production in 1989. As generation capacity fell to 180MW, its repowering project started in 2016 with World Bank funding. The project was scheduled to be completed in June 2019.

In a report, the World Bank said the project would more than double the generation output with only a 30% increase in gas requirement. Consequently, specific fuel consumption will be reduced by 44%.

According to the Power Division, a contract was signed with China Energy Engineering Group in June 2016 for the repowering of the 4th unit.  A new turbine model having an advanced gas path with a capacity of about 240MW has been installed by the engineering, procurement and construction (EPC) contractor and the plant has been running in simple cycle mode since 30 October 2018.

Under the project, the EPC contractor supplied a new gas turbine, a generator, a heat recovery steam generator and associated auxiliaries. The existing 210MW turbine is used for a combined cycle. After finishing the pre-commissioning work, the combined steam turbine was put into rolling mode and reached 3,000 revolutions per minute but failed to synchronise due to high shaft vibration.

The turbine was synchronised on 23 July 2020.  But it was shut down due to high shaft vibration. After checking, the EPC contractor again started commissioning on 9 October 2020. But the vibration was still high.

After completion of the pre-commissioning work of the combined cycle of the project, when the existing steam turbine was set rolling, it stopped due to high shaft vibration.

It showed that the power generation is 240MW. That means 169MW less electricity is being produced.

According to a Power Division report, the EPC contract does not include any work on a steam turbine. As the required equipment for steam turbines is not installed, production is not going on as per target.

In this situation, two new portions are being added to the rectification works of the existing steam turbine, spare parts, and consumable items of GT under LTSA (Long Term Service Agreement) by correcting the project of the desired power production.

When the project was approved in 2016, its cost was estimated at Tk2029 crore. In the first amendment in 2019, the project time was extended by two years and the cost was increased to Tk2072 crore. The project was again extended by another year.

According to sources in the Bangladesh Power Development Board, it has so far paid Tk1,465 crore for the project.

In the new amendment proposal, the cost of the project is further being increased by Tk99.45 crore to Tk2171 crore. At the same time, the deadline is being extended by one and a half years.

Power Division Secretary Md Habibur Rahman said due to vibration, the steam turbine of this unit could not be synchronised yet. Therefore, even if electricity production is less than the target, production will be as per target once it is synchronised.

Seeking anonymity, a senior official involved with the project said since the feasibility study did not suggest the replacement of the steam turbine in their report, it was not included in the project.

"But the fault of the steam turbine was found while running the power plant after the physical work. Without fixing the problem, it will not be possible to achieve the desired capacity," he added.

He said the feasibility of the project was carried out in 2012 when the existing steam turbine was 23 years old. But now it has risen to 33 years.

Generally, the economic life of machinery is only 25 years. Naturally, the existing steam turbine cannot ensure output now.

However, if the steam turbine is replaced with a new one, it will be possible to generate electricity from the plant at the desired capacity, he said, adding an additional Tk100 crore to Tk150 crore will be needed for this.

But energy experts say the feasibility study might not have been done properly. For this reason, the report did not mention what equipment was required. 

Professor M Shamsul Alam, energy adviser to the Consumers Association of Bangladesh (CAB), told The Business Standard the EPC contractor will have to take responsibility for this.

"Because the contractor will do whatever is required to increase the power generation capacity of the 210MW unit to 409MW. There is scope to realise compensation for their failure. The Power Division should take action in this regard," he added.

After a lengthy discussion with the EPC contractor, the Power Division took the initiative to include the new portions in the project. Proposals for the extension of the project cost and duration have been sent to the Planning Commission.

At present, there are 154 government and private power plants in the country, with a total production capacity of 22,512MW, although production is 11,000MW to 13,000MW at present.

Bangladesh / Infograph / Top News

Ghorashal Power Plant / Power plant bangladesh

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Is the IMF to blame for growing pressure on your wallet?
    Is the IMF to blame for growing pressure on your wallet?
  • Dr Salehuddin Ahmed. Illustration: TBS
    Reforms in banking must to sustain financial sector
  • Why 2012 reforms were not done is a million-dollar question
    Why 2012 reforms were not done is a million-dollar question

MOST VIEWED

  • Shipped Bhola gas to cost higher, yet cheaper than spot LNG
    Shipped Bhola gas to cost higher, yet cheaper than spot LNG
  • Electric power transmission pylon miniatures and Adani Green Energy logo are seen in this illustration taken, December 9, 2022. REUTERS/Dado Ruvic/Illustration/Files
    India rules out involvement in Adani power deal with Bangladesh
  • PMO cuts expenditures for electricity and others: official
    PMO cuts expenditures for electricity and others: official
  • Collage: UNB
    BPDB seeks revised agreement with Adani before importing power from Jharkhand plant
  • File photo
    No sigh of relief as LPG price hiked by Tk266 per 12kg cylinder
  • Representational image. A liquefied natural gas (LNG) tanker is tugged towards a thermal power station in Futtsu, east of Tokyo, Japan November 13, 2017. REUTERS/Issei Kato
    Govt resumes importing LNG from int'l spot market

Related News

  • Opec to give $38m for Bangladesh power plant development
  • Bengal Electricity inaugurates commercial Power Plant in Cumilla
  • Power supply in Dhaka: Until Ghorashal working in full capacity, situation not to improve
  • Ghorashal power plant’s unit 5 resumes production after 7 days
  • Power generation at unit 5 of Ghorashal power plant halted since national grid failure

Features

Andy Mukherjee. Sketch: TBS

What makes India's billionaires' support special for Adani

18h | Panorama
Photo: Rejaul Hafiz Rahi

A jackal farewell

19h | Earth
The trio spearheading the revival of book cover designs

The trio spearheading the revival of book cover designs

20h | Panorama
Six Jeep Wranglers and a special XJ Jeep Cherokee set out into the depths of Lalakhal, Sylhet for an experience of a lifetime. Photo: Ahbaar Mohammad

Jeep Life Bangladesh: A club for Jeep owners to harness the power of their vehicles

1d | Wheels

More Videos from TBS

A proper price formula can help investors to plan big

A proper price formula can help investors to plan big

1d | TBS Round Table
Rumors about Sarika that everyone thinks are true

Rumors about Sarika that everyone thinks are true

1d | TBS Entertainment
Mugging rife in Tejgaon, murder in Wari

Mugging rife in Tejgaon, murder in Wari

1d | TBS Current Affairs
What secrets are hidden behind Adani's wealth?

What secrets are hidden behind Adani's wealth?

1d | TBS Stories

Most Read

1
Bapex calls candidates for job test 9 years after advert!
Bangladesh

Bapex calls candidates for job test 9 years after advert!

2
Leepu realised his love for cars from a young age and for the last 40 years, he has transformed, designed and customised hundreds of cars. Photo: Collected
Panorama

'I am not crazy about cars anymore': Nizamuddin Awlia Leepu

3
Photo: Collected
Energy

8 Ctg power plants out of production

4
The International Monetary Fund (IMF) logo is seen outside the headquarters building in Washington, U.S., September 4, 2018. REUTERS/Yuri Gripas/File Photo
Economy

IMF approves $4.7 billion loan for Bangladesh, calls for ambitious reforms

5
Photo: Collected
Court

Japanese mother gets guardianship of daughters, free to leave country

6
Fund cut as Dhaka's fast-track transit projects on slow spending lane
Infrastructure

Fund cut as Dhaka's fast-track transit projects on slow spending lane

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net