Bangabandhu tunnel: 92% construction works completed
Skip to main content
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
The Business Standard

Sunday
January 29, 2023

Sign In
Subscribe
  • Home
  • Economy
    • Aviation
    • Bazaar
    • Budget
    • Industry
    • NBR
    • RMG
    • Corporates
  • Stocks
  • Analysis
  • World+Biz
  • Sports
  • Features
    • Book Review
    • Brands
    • Earth
    • Explorer
    • Fact Check
    • Family
    • Food
    • Game Reviews
    • Good Practices
    • Habitat
    • Humour
    • In Focus
    • Luxury
    • Mode
    • Panorama
    • Pursuit
    • Wealth
    • Wellbeing
    • Wheels
  • Epaper
  • More
    • Subscribe
    • Videos
    • Thoughts
    • Splash
    • Bangladesh
    • Supplement
    • Infograph
    • Archive
    • COVID-19
    • Games
    • Long Read
    • Interviews
    • Offbeat
    • Podcast
    • Quiz
    • Tech
    • Trial By Trivia
    • Magazine
  • বাংলা
SUNDAY, JANUARY 29, 2023
Bangabandhu tunnel: 92% construction works completed

Bangladesh

BSS
30 October, 2022, 04:45 pm
Last modified: 31 October, 2022, 02:27 pm

Related News

  • PM likely to open 25 projects in Rajshahi on Sunday
  • Release of 24,000 Karnaphuli encroachers' names demanded
  • Bangabandhu tunnel to open to traffic around April-May: Quader
  • Conduct eviction drive on Karnaphuli river banks or face lawsuit: Environmentalists to Ctg DC
  • Motorcycles, three-wheelers not allowed in Bangabandhu Tunnel

Bangabandhu tunnel: 92% construction works completed

BSS
30 October, 2022, 04:45 pm
Last modified: 31 October, 2022, 02:27 pm
Photo: BSS
Photo: BSS

The construction works of the much-awaited Bangabandhu tunnel under Karnaphuli River aimed at connecting the Chattogram city to the southern part of the district is expected to be completed by December this year.

The project officials hoped that the construction works of the tunnel will be finished within the stipulated time.

Around 92% construction works of the Tunnel has been completed and the construction of the cross passage and tunnel related toll plaza is also nearing completion, the concern sources added.

The sources said, the mechanical, electrical and civil works of the tunnel are also almost completed. One of the two tubes is planned to open to traffic in November, the sources said.

Project director Harunur Rashid Chowdhury said the work of four lane of two tubes has been completed, even other related works are also in final stages.

"Around 92% construction works has been completed till today. At present the construction works of drainage system, installation of pumps is going on," he added.

Terming the tunnel tube would be opened by December Harunur Rashid Chowdhury said two tubes are being constructed within an 11-metre gap so that heavy vehicles can pass through the tunnel easily.

'We have completed the mechanical, electrical and civil works of the tunnel and the construction of the cross passage and tunnel related toll plaza is also nearing completion," he added.

According to the project officials, the length of the under-construction tunnel will be 3.40 kilometres with an approach road of 5.35 kilometres alongside 727 metres of a bridge linking the main city, port and western side of the river with its eastern side.

Bangabandhu daughter Prime Minister Sheikh Hasina inaugurated the  work of the first tunnel tube On February 24, 2019.

China Communications Construction Company Ltd is working as the contractor for the project.

The tunnel will connect the proposed Asian Highway to Dhaka-Chattogram-Cox's Bazar Highway and will reduce the distance from Chattogram to Cox's Bazar by 40-km. Vehicles in this tunnel will run at a speed of 80-km per hour – sources said.

The project was supposed to be completed by 2020. However, in 2018, the duration of the project was extended until December 2022 and the cost of the project was revised to Tk10,374 crore.

The Exim Bank of China is giving a loan of Tk5,913 crore with two percent interest rate for the project while the Bangladesh government is funding the rest.

The tunnel will be the first under-river tunnel in South Asia. Extensive work is underway to complete the remaining eight percent of the project. Project Director Harunur Rashid Chowdhury said, the domestic and foreign engineers and workers involved in the project are advancing the work by facing challenges everyday. 

Top News

Bangabandhu Tunnel / project / Karnaphuli river

Comments

While most comments will be posted if they are on-topic and not abusive, moderation decisions are subjective. Published comments are readers’ own views and The Business Standard does not endorse any of the readers’ comments.

Top Stories

  • Photo: Mumit M/TBS
    Biz leaders want crisis management, energy security for survival
  • A proper price formula can help investors to plan big
    A proper price formula can help investors to plan big
  • SK Bashir Uddin: TBS sketch
    Investments risky without consistent policy, reliable data

MOST VIEWED

  • Picture: Collected
    US Embassy condemns recent incidents of visa fraud
  • Four top bankers arrested in DSA case filed by S Alam group 
    Four top bankers arrested in DSA case filed by S Alam group 
  • Photo: Saqlain Rizve
    Bangladeshi university students identified as problematic users of Facebook, internet: Study
  • Bapex calls candidates for job test 9 years after advert!
    Bapex calls candidates for job test 9 years after advert!
  • Matarbari coal-power plant, one of the projects funded by Japan International Cooperation Agency (Jica)-funded projects.
    More than 50% Japan-funded projects lagging behind
  • Ctg Port Gets A Boost: The Chattogram port officially starts to berth vessels with 10 metres drought on Monday. As of now, only 9.5m draught vessels could anchor at the port, each carrying 2,500 TEUs. But the 10m draught ship will be able to carry 4,000 TEUs, bumping up the port’s container handling capacity and bringing down costs. The photo was taken recently from the port area. Photo: Mohammed Minhaj Uddin
    Dollar crisis: 3 ships with 54,000 tonnes of goods get stuck at Ctg port

Related News

  • PM likely to open 25 projects in Rajshahi on Sunday
  • Release of 24,000 Karnaphuli encroachers' names demanded
  • Bangabandhu tunnel to open to traffic around April-May: Quader
  • Conduct eviction drive on Karnaphuli river banks or face lawsuit: Environmentalists to Ctg DC
  • Motorcycles, three-wheelers not allowed in Bangabandhu Tunnel

Features

Snipe in flight. Photo: Enam Ul Haque

Baikka Beel: 'A world where snipe work late'

10h | Panorama
Photo: Noor-A-Alam

Pet cafes: Where love for food and animals cohabit

12h | Food
Illustration: TBS

How MFS is turbocharging national economy

15h | Thoughts
Now is the time to focus on FDI composition

Now is the time to focus on FDI composition

16h | Panorama

More Videos from TBS

What does Shahrukh has in his 770 million dollar property?

What does Shahrukh has in his 770 million dollar property?

5h | TBS Entertainment
15 Reasons Your Entrepreneurial Career Can Fail

15 Reasons Your Entrepreneurial Career Can Fail

4h | TBS Career
Women are going to make history in match management in cricket

Women are going to make history in match management in cricket

3h | TBS SPORTS
Gold covered mummy discovered in Egypt

Gold covered mummy discovered in Egypt

9h | TBS World

Most Read

1
Picture: Collected
Bangladesh

US Embassy condemns recent incidents of visa fraud

2
Four top bankers arrested in DSA case filed by S Alam group 
Bangladesh

Four top bankers arrested in DSA case filed by S Alam group 

3
Illustration: TBS
Banking

16 banks at risk of capital shortfall if top 3 borrowers default

4
Photo: Collected
Splash

Hansal Mehta responds as Twitter user calls him 'shameless' for making Faraaz

5
A frozen Beyond Burger plant-based patty. Photographer: AKIRA for Bloomberg Businessweek
Bloomberg Special

Fake meat was supposed to save the world. It became just another fad

6
Representational Image
Banking

Cash-strapped Islami, Al-Arafah and National turn to Sonali Bank for costly fund

EMAIL US
contact@tbsnews.net
FOLLOW US
WHATSAPP
+880 1847416158
The Business Standard
  • About Us
  • Contact us
  • Sitemap
  • Privacy Policy
  • Comment Policy
Copyright © 2023
The Business Standard All rights reserved
Technical Partner: RSI Lab

Contact Us

The Business Standard

Main Office -4/A, Eskaton Garden, Dhaka- 1000

Phone: +8801847 416158 - 59

Send Opinion articles to - oped.tbs@gmail.com

For advertisement- sales@tbsnews.net